Voting Results from CDBG Additional Funding Poll Now Available

On September 11, 2025, Terrebonne Parish President Jason Bergeron announced that TPCG was able to reallocate $2 million to OCD-approved projects around Terrebonne Parish. In an effort to give Terrebonne Parish residents the chance to be heard, a public poll was created for residents to share where they thought additional funds should be allocated. 910 votes were cast for 27 possible projects, and the results are in. Check out the projects and total number of votes below: 

Project Votes
Activate the Bayou Phase I: Boat Launches 245
Main Street Improvements 137
Improvements for Critical Evacuation Routes 82
Activate the Bayous Phase II: Dredging  79
Stormwater Management Master Plan 52
Support the Seafood Industry Phase I: Grants 36
Small Business Grants 29
Waterline Quality and Redundancy 28
Steam Center 25
Bayou Terrebonne Pump Station 25
Housing and Human Services Annes and Community Center 22
Aviation Workforce Development at Fletcher - Terrebonne 22
Parish-Wide Weather Stations 20
Bayou Lafourche Pump Station 14
Permanent Facility for HHS (Shamrock Building) 14
Bayou Black Pump Station 13
Facade/Site Improvements 9
Wastewater Implementation 9
TPDS - Permanent Location for LMTCT 9
Support the Seafood Phase III: Implementation 8
Support the Seafood Industry Phase II: Plan 6
Wastewater Management Plan 5
Bayou Cane Detention Basin and Berm 5
Small Business Incubator (The Nest) 5
Community Resilience Centers Phase II 5
Relocation of Garbage Transfer Facility  4
Community Resilience Centers Phase I: Feasibility Study 2
Total 910

These results give us insight to the needs of our community and will prove invaluable as we work to reallocate funding.